The Brief
To supply a 55 sqm Modular Operating Theatre with anesthetic, prep, scrub and two bed recovery unit to a first floor alcove over an existing flat roof scanning suite.


Time Scale
Order Date: End December 2007
Site Delivery: June 2008
Operational: August 2008
The Solution
A steel framed 7 module unit was manufactured (1st and second floor). The building was manufactured with top half clad in louvered panels, with the whole building finished in a terracotta colour to match the existing buildings. A steel matrix was designed and installed to support the new theatre.


The modules were manufactured in a eight week period and erected on site in one day, with connection to existing structure and commissioning taking a further eight weeks.

tel 01623 651211 fax 01623 624756
email info@medi-cell.biz

 

 

Web development by Xposure Creative brand marketing

 

Unique Features
• Easily re locatable structure
• Structurally designed to take load of another floor
• Steel work substructure to avoid loads through the existing building.

Value
£1.25 million